Direct answer: freeze the whole wet-floor assembly, not only the drain position

Before screed, the team should agree one coordinated drawing that connects the structural or base floor, drainage outlet, drain body, waterproofing system, finished floor levels, threshold, tile build-up and enclosure line. The drawing should show where water is intended to travel and where it must be contained. It should also identify who checks the work and at what point. A drain marked on a plan is not enough: the same decision affects the floor geometry, tile cuts, glass support, door clearance and maintenance access. Product data and site dimensions should replace nominal assumptions before concealed work proceeds.

Start with fixed levels and the threshold decision

Establish the relevant level references first: the adjacent bathroom finish, the intended shower finish, the available floor recess or build-up, and the drainage connection. Then decide whether the entrance is flush, gently transitioned or formed with a kerb. A flush entrance can improve visual continuity, but it leaves less tolerance for uncoordinated build-ups and must still satisfy the project’s containment, accessibility and construction requirements. Check the door swing, bathmat position and route out of the shower too. The important output is a dimensioned section using the selected finishes and products, not a generic sketch.

  • Existing and proposed finished-floor levels
  • Available recess and build-up depth
  • Threshold profile and adjoining finish
  • Drain outlet route and access constraints

Treat drainage and waterproofing as one interface

The drain must connect to the chosen waterproofing approach as a complete system. Its flange or collar, corners, wall-to-floor junctions, penetrations and termination at the shower entrance all need compatible details. Tiles and grout are finishes, not the water-control layer by themselves. Ask for the current manufacturer information for the exact drain and waterproofing products, then have the appointed specialists resolve any mixed-system interfaces. The pre-screed review should also name the hold points for substrate inspection, waterproofing review and any project-required testing before tiles conceal the assembly. These are professional checks, not homeowner installation steps.

Use the tile module to test the floor planes

A point drain normally produces several floor planes; a linear drain may allow a simpler principal fall, depending on its position and the room geometry. Neither choice is automatically better. Overlay the proposed tile grid on the planned falls and inspect the perimeter, drain edges and threshold. Large tiles may need deliberate cuts to follow compound planes, while mosaics create more joints and a different cleaning character. Coordinate actual tile thickness, adhesive allowance and grate adjustment range. A small setting-out study can reveal awkward slivers, uneven perimeter lines or a grate that cannot finish neatly with the selected tile.

  • Drain centred, offset or against a wall
  • Single-plane or multi-plane floor geometry
  • Tile thickness and surface suitability
  • Perimeter cuts, grate alignment and edge trims

Coordinate glass, controls and fittings before the floor closes

Set out the enclosure line at the same review. Glass channels, clips or hinges may meet the wet floor, wall backing or threshold; their positions cannot be guessed after waterproofing. Confirm the shower opening, splash exposure, screen length, door movement and cleaning reach. Locate controls so a user can operate the shower without an awkward step into the spray, subject to the selected fittings and design. Shelves, benches and grab-support provisions also affect junctions and backing. The aim is not to turn every item into a floor penetration, but to prevent late drilling or incompatible support decisions.

Planning example

Planning example: a fictional bathroom concept uses a flush walk-in shower, a wall-adjacent linear drain and large porcelain floor tiles. The initial plan shows the drain but not its depth or grate length. During coordination, the team records the actual drain data, surveys the outlet, draws the full floor section and overlays the tile module. The review reveals that the intended grout line would leave a narrow cut beside the grate and that the glass channel conflicts with the entrance junction. The design is adjusted on paper: the tile grid moves, the grate length is confirmed and the glass fixing strategy is revised. The example shows why the decisions belong together.

  • Input: measured floor and outlet
  • Decision: threshold and drain system
  • Proof: section plus tile overlay
  • Release: named inspections before covering

Pre-screed review checklist

Use this as a coordination checklist rather than an installation method. The project team should adapt it to the selected system, site condition and applicable requirements.

  • Surveyed dimensions and level datum are recorded
  • Exact drain model, outlet and connection are identified
  • Floor build-up and threshold section are approved
  • Waterproofing-to-drain and perimeter details are issued
  • Tile module, thickness, grate and edge details align
  • Glass line, fixings and wall backing are coordinated
  • Inspection, testing and photographic records are assigned
  • Cleaning access and removable drain components are understood

Limitations and the next useful step

A journal checklist cannot determine the correct construction for a particular bathroom. Existing slabs, landlord rules, accessibility needs, drainage capacity, waterproofing warranties and manufacturer details can change the solution. Avoid setting a universal fall, build-up or testing procedure without the appointed professionals reviewing the actual project. The next useful step is a short pre-screed coordination review using the measured room, the selected drain, waterproofing data, tile sample and proposed glass details. Record the agreed section, responsibilities and hold points before authorising concealed work. That small package gives the site team one reference and gives later quality reviews something specific to inspect.

Sources & further reading

Make this useful for your project.

A review of your property and priorities can turn general guidance into a defined brief.

Explore Walk in showersDiscuss your project
Return to the journal