Direct answer
A bathroom delivery and pre-installation register should confirm each product’s approved reference, finish, quantity, visible condition, included components, documentation, storage location and release status before it is installed. It should link the purchase order and approved fixture schedule to the physical basin, WC, bath, tap, shower fitting, mirror, accessory or furniture piece that arrived. The check is more than counting cartons. Duravit’s product instructions explicitly call for inspection for damage before installation and require product-specific pre-installation information to be followed. A simple hold, accept or query status prevents the programme from turning an unverified delivery into a concealed defect or an incompatible opening on site.
Build the register from the approved schedule
Start with the latest controlled fixture and fitting schedule, not the supplier invoice alone. Give every item a room code and unique reference, then list manufacturer, product code, size, finish, handedness, quantity, required accessories and related drawing. Separate the main item from components that may ship in different cartons: frames, wastes, traps, flush plates, valves, legs, brackets, hoses, fixings, control modules and specialist tools. Product compatibility is model-specific. Duravit’s professional portal directs installers to technical drawings, assembly documents and compatibility information by product reference, which is why a generic description such as white basin or chrome tap is not enough to release work.
- Room and fixture reference
- Manufacturer and exact product code
- Size, finish and orientation
- Required companion parts
- Approved drawing and schedule revision
Inspect condition without losing protection
Agree where and when inspection happens and who may open protective packaging. Photograph cartons before opening, including visible impact, water exposure or crushed corners. Check accessible surfaces under neutral light for chips, cracks, scratches, finish variation, deformation or missing protective film, while handling the product according to supplier guidance. Keep small components together and do not place heavy fittings loose inside a bath, basin or vanity. After inspection, restore protection and mark the package with the internal register reference without covering manufacturer labels. A product can pass a visual check and still remain on hold if its dimensions, components or installation information are unresolved.
Verify interfaces before installation release
Use the actual product and current technical drawing to recheck critical interfaces: rough-in positions, carrier or frame, wall depth, finished floor level, worktop cut-out, tap reach, overflow, waste arrangement, concealed body, electrical or control provision and service access. This is a coordination review, not an instruction to modify plumbing or wiring. Product families can look similar while using different connection sets or pre-installation dimensions. Duravit’s mounting documents distinguish the product, pre-installation sheet and qualified installer responsibilities. Release the item only when the installed setting can follow the selected manufacturer’s information and the project drawings agree with it.
Planning example
Planning example: a master bathroom receives two countertop basins, wall-mounted taps, a concealed WC frame and a shower set. The invoice and carton quantities appear correct. Inspection finds that one basin has the right collection name but a different width, one tap trim arrived without its matching concealed body, and the flush plate finish differs from the approved sample. The register places those three lines on hold, photographs the references and keeps the correct basin and shower components protected for later installation. This fictional scenario demonstrates receipt control; it is not a supplier claim, installation instruction or completed project.
Separate acceptance from installation readiness
Use two decisions. Receipt acceptance confirms that the delivered item matches the order and has no visible issue found during the agreed check. Installation readiness confirms that the room, substrate, services, support, associated components and latest drawings are ready for that exact item. A basin may be accepted but not ready because the worktop template is pending; a tap may be correct but held because its concealed body has not been verified. This distinction protects both product and programme. It also makes responsibility clearer when an item is stored for several weeks between delivery and installation. Record who changes status and on what evidence.
- Received and counted
- Identity and finish verified
- Condition inspected
- Components reconciled
- Interface checked
- Released for installation
Checklist before fixtures leave storage
Run the checklist in a protected, well-lit area with the approved schedule and manufacturer information available. Keep disputed products segregated.
- Match room code, product code, size and finish
- Count all cartons and separately supplied accessories
- Photograph packaging and visible product condition
- Check handedness, orientation and colour variation where relevant
- Confirm frames, bodies, wastes, traps, valves and fixings
- Link current technical drawings and installation documents
- Review rough-ins, supports, cut-outs and service access
- Record storage location and protection method
- Mark accept, hold or query with owner and date
- Retain supplier correspondence and resolution evidence
Limitations and specialist responsibility
This register does not prove concealed product integrity, certify a fixture, override supplier terms, diagnose manufacturing defects or authorise unqualified installation. Plumbing, electrical, structural support, waterproofing and product assembly remain the responsibility of the appointed professionals using current manufacturer instructions and verified site conditions. Complaint and notification periods vary by supplier and contract, so confirm the applicable terms rather than relying on a generic number of days. Ceramic and finish tolerances can also be product-specific. Do not attempt to repair chips, alter components or substitute connectors to keep the programme moving; record the issue and obtain the responsible party’s written decision.
Next step: hold a room-by-room release review
Before installation starts, bring the accepted products, current schedule, technical drawings and site setting together room by room. Reconcile all components, confirm protection and photograph each released item with its reference. Put missing or disputed lines on the short-term procurement and programme list, then update dependent tasks such as worktop templating, wall close-up or glass measurement. At handover, retain product references, manuals, supplier records and care information with the final fixture schedule. This creates a traceable path from approved selection to delivered product and helps future maintenance identify the actual model without dismantling the bathroom or relying on an old showroom description.